LED R&D Lab(VD)
79
⑦ After the first stage installation is finished, from the second stage, install the upper and lower
docks without cables in the same direction.
Be sure to remove the attached protective sheet before installing the common surface.
※ When docking up and down, the horizontal shared surface must be assembled, but the shared surface is inserted between the
front and the frame (Fig. 1).
※ After assembling the shared surface, fix it with FH screw.(Fig. 2)
※ Install docking in the same way as 3, 4, 5, 6 levels.
Fig.1 Assembling the horizontal shared plane Fig.2 Fixed with shared face screw
FRAME
FRONT
◇ CABINET installation (IWA P1.26)
[ UHD SCREEN (36Cabinet) ]
5. Cabinet + Frame installation
SCREW-MACHINE
(FH, M4, L10)
Protective Sheet