Commissioning guidelines
Procedure
Proceed as follows to commission the inverter:
Define the requirements of
your application placed on
the drive.
→ (Page 68) .
Reset the inverter when
required to the factory
setting.
→ (Page 72) .
Check whether the factory
setting of the inverter is
appropriate for your
application.
If not, start with the basic
commissioning.
→ (Page 74).
If necessary, set further
functions in the inverter.
→ (Page 99) .
Save your settings.
→ (Page 169) .
You have commissioned the inverter.