Commissioning
6.2 Preparing for commissioning
SIMATIC ET 200pro FC-2 converter
68 Operating Instructions, 04/2015, FW V4.7.3, A5E34257324B AB
Preparing for commissioning
Overview
Before starting commissioning, you must know the answer to the following questions:
●
What are the data specifications of my inverter?
→ Description (Page 21).
●
→ Factory setting of the inverter control (Page 69).
●
What technological requirements must the drive fulfill?
→ Selecting the control mode (Page 70).
→ Defining additional requirements for the application (Page 71).
Before starting commissioning, you must know the following data:
●
Which motor is connected to the inverter?
Note down the Article No. of the motor and the motor’s nameplate data.
If available, note down the motor code on the motor’s nameplate.
●
In which region of the world is the motor to be used?
- Europe IEC: 50 Hz [kW]
- North America NEMA: 60 Hz [hp] or 60 Hz [kW]
●
How is the motor connected?
Pay attention to the connection of the motor (star connection [Y] or delta connection [Δ]).