Commissioning
6.5 Basic commissioning
SIMATIC ET 200pro FC-2 converter
80 Operating Instructions, 04/2015, FW V4.7.3, A5E34257324B AB
Go online and start the configuration wizards
Procedure with STARTER
Proceed as follows to start configuration of the inverter:
Select your project and go online: .
In the following screen form, select the inverter with
which you wish to go online.
Download the hardware configuration found online in
your project (PG or PC).
Significance of the symbol in front of the inverter:
(A) The inverter is online.
(B) The inverter is offline
When you are online, double-click on "Control Unit".
Start the configuration wizards:
You have started to configure the inverter.
Carry-out basic commissioning
Procedure
Proceed as follows to carry out basic commissioning:
See also Section: Selecting the control mode (Page 70)