4. For each ceiling feed-through drill a hole of ・ 12 mm through the false
ceiling.
5. Calculate the necessary length for air sampling hose and cut it. Tuck the
cut hose through the intermediate ceiling and on the hose pin at the pipe
cap of the air sampling pipe. If necessary, please heat the hose by hot
air gun.
NOTICE
The whole of aspiration reducing film sheet must be located over the open-
ing of pipe cap directly. The diameter of opening in the aspiration reducing
film sheet must not be changed.
To keep the glued surface of the film clean from dust and grease, please
avoid any contact.
WARNING
The air sampling hose cannot be monitored during the application of ceiling
ducts with up-streamed aspiration reduction within the T-pieces (pipe
caps).