B95W
Maintenance
06_Wartung und Pflege_en.fm - V1.0 - 1.8.17
191 / 306
6
20
Check slewing break
Fig. 6-39 Check slewing break
1 Digging tool straightened
2 Uppercarriage at 45°
Park vehicle on level, solid ground.
Raise vehicle fully using the support function.
Adjust digging tool for maximum reach (1).
Retract bucket.
Turn uppercarriage by 45° (2).
Retract bending cylinder fully.
Lower digging tool until the bucket is floating around 10 cm above the ground.
Align the side edge of the bucket/building tool with a reference point in your
environment. Remember this point of reference.
Stop the engine.
Wait one minute (machine operator must not leave the machine).
Look at the reference point during this waiting period (one minute).
If the building tool has not moved from its alignment with the point of reference,
the excavator may be operated further.
If the building tool has moved out of alignment with the reference point, cease
operations as the excavator is not in a usable condition, and contact an
authorized specialist workshop.
1 2