B95W
Initial installation and settings
04_Erstinstallation und Einstellungen_en.fm - V1.0 - 1.8.17
47 / 306
4
48
4 Initial installation and settings
4.1 Initial instruction
The attaching of the attachable equipment and commission thereof should only
be carried out by qualified technicians.
The machine must only be operated by properly trained and instructed personnel.
For this purpose, appropriate instruction and training are provided when the
machine is handed over.
4.1.1 Hand over the machine and instruct the operator.
The following checklist should be followed when handing over the machine to
the operator:
Operating
instructions
Go through the operating instructions (page by page) and explain them in
detail through practical training on the machine.
Items which are particularly important include:
• Accident Prevention Regulations published by the employer’s liability
insurance associations in the user's country
• Technical data
• Control, indicating, and warning elements
• Checks before commissioning the machine
• Engine running-in instructions
• Starting and shutting down the engine
• Explanation of the hydrostatic travel drive
•Driving
• Recovery and transport of the machine
• Operation of all functions
• Explanation of maintenance and inspection intervals according to
maintenance and inspection plan by demonstrating maintenance points
on machine
• Lubrication intervals and lubricating points according to overview of
lubricating points and demonstration of these points on the machine
• Handing over the engine operating instructions
Notice
An initial inspection must be carried out before commissioning.
See chapter 6.6.1 “Initial inspection (delivery inspection)”.