ACS2000 User manual 2UEA001270 Rev. F 6-15 (16)
Chapter 6 - Electrical installation
6.7.2 Cable preparation
The control cables are entered either through the top or the bottom of the
terminal entry unit.
Punch the aluminum plate being used for cable entry as required for the
cables.
6.7.2.1 Cable routing
Route the cables through the steel access plate to termination on the right
side wall in the control compartment where the IOEC I/O control
connections and the fieldbus interface devices are rail mounted.
See Chapter 2 - Power electronics and cabinet features, 2.4.1 Auxiliary
power supply for auxiliary current and power specifications.
Figure 6-12 Auxiliary, control, and fieldbus cable entry
6.7.2.2 Determining the cable length
Determine the required length of a cable between the point of entry and
the connection point inside the cabinet and cut the cable to the required
length before connection to avoid excess cable in the raceway.
Legend
1 Top access panel
2 Top cable route
3Customer
raceway
4 Bottom cable
route
5 Bottom access
panel
6 PE terminals
7 Standard IOEC2
customer
communication
module
8 Optional IOEC4
customer
communication
module
1
2
3
4
5
6
6
6
6
8
7

Table of Contents