ACS2000 User manual 2UEA001270 Rev. F 7-3 (6)
Chapter 7 - Commissioning
Commissioning checklist
Mechanical installation
Electrical installation
1 Drive installed according to the instructions in the User manual
2 Drive securely fastened to the floor (if applicable)
3 Fan outlet box or optional redundant fan unit installed
4 Visual inspection:
- no loose or damaged components
1 Types and cross sections of control cables suitable for the signal type and signal level
2 Types and cross sections of power cables selected according to the ABB power cable
specification
3 Pulse encoder cable shields connected to “shield grounding point” and not connected
directly to the pulse encoder interface (only applicable for drives with pulse encoder
option)
4 Cable entry made according to the instructions in the User manual
5 All control cable shields and conductors are connected according to the instructions of
the User manual, appropriately labelled, and the customer-side connections are
completed
6 Ground cable of drive securely connected at both ends and power cable shields
grounded at both ends
7 Line supply and motor cables not connected at both ends (cables and drive must be
meggered before connection)