© Agilent Technologies 1989–2002 Agilent 3070 / 79000 Site Preparation 10-78
Chapter 10: Site Preparation – Power Requirements for Older Systems: Series 3 Power Requirements and Connections (Prior to May 2000)
Series 3 Power
Requirements and
Connections (Prior
to May 2000)
This section contains:
■ Introduction, 10-78
■ Series 3 / 79000 Power Requirements, 10-80
■ Power Recommentations, 10-82
■ Sizing The Input Wires And Circuit Breakers, 10-89
■ Connecting Power To The Testhead, 10-90
■ “Mains” Wiring Diagrams, 10-101
■ 220/380–240/415 V 3-Phase Wye with Neutral (0E5,
05L, 0E7), 10-102
■ 220/380–240/415 V Single-Phase Wye with Neutral
(05B, 05G, 05K), 10-102
■ 120/208–127/220 V 3-Phase Wye with Neutral (AWW,
05E), 10-103
■ 120/208–127/220 V Single-Phase Wye with Neutral
(AWV, AWZ), 10-104
■ 200-240 3-phase Delta (0ED, 05C, 05H, 0E6), 10-105
■ 100/200-120/240 V Single-Phase Center-Tap Neutral
(AWY, 0E3, 0EG, 0EH), 10-106
■ 220–240 V Single-Phase Earthed (05M, 05F, 05J),
10-107
■ 200–240 V Single-Phase Non-Earthed (AWX, 0EB, 0EJ,
0EC), 10-108
Introduction
This remaining sections of this chapter describe the
electrical power requirements for 3070 Series 3 or
79000 family board test systems which have serial
numbers shown in
Table 10-5 and Table 10-6. See
Appendix 10,
Connecting Power to the E1135A/B
PDU for systems with serial numbers shown in Table
10-7 on page 10-79.
NOTE
If you are installing a new Agilent 3070 / 79000
Series 3 system with a serial number higher than
those shown below, go to
Series 3 Power
Requirements and Connections (Prior to May
2001) on page 10-5.
NOTE
The Customer Engineer (CE) who does the
installation has the responsibility of removing the
testhead from the pallet. Therefore, the system
power cannot be installed until after the CE has
removed the system from the pallet.