Maintaining the Split/Splitless Inlet 5
Maintaining Your GC 65
9
Blow the inside of the inlet dry with compressed air or
nitrogen.
10 Install the gold seal and reducing nut.
11 Install the liner and O- ring.
12 Install the column. (See “To Install a Capillary Column
with the Split/Splitless Inlet” on page 48.)
13 Check for leaks.
14 Bakeout contaminants. (See “To Bakeout Contaminants
from the Split/Splitless Inlet” on page 66.)
15 Restore the analytical method.
16 Reset the septum and liner EMF counters. See To Reset
an EMF Counter in the Operation Manual.