7 Commissioning of the Frequency Inverter
7.1 Switching on Mains Voltage
After completion of the installation work, make sure to check all control and power
connections again before switching on the mains voltage. If all electrical connections
are correct, make sure that the frequency inverter is not enabled (control input S1IND
open). After power-up, the frequency inverter carries out a self-test and the relay
output (X10) reports "Fault".
After a few seconds, the self-test is complete, the relay (X10) picks up and signals "no
fault ".
If the unit is in "as-delivered" condition or after resetting the unit to the factory set-
tings, the guided commissioning procedure is started automatically. On the control
unit, the “SetUP“ menu from the menu branch CTRL is displayed.
7.2 Setup Using the Control Unit
The guided commissioning of the frequency inverter determines all parameter settings
relevant to the required application. The available parameters were selected based on
known standard drive applications. This facilitates the selection of the important pa-
rameters. After successful completion of the SETUP routine, the actual value
Actual
frequency
241 from the VAL menu branch is displayed on the control unit. Now, the
user should check whether further parameters are relevant for the application.
Note: The guided commissioning contains the function for parameter identifica-
tion. The parameters are determined by way of measurement and set
accordingly. In the case of higher requirements as regards the accuracy of
the speed/torque control, you should carry out the guided commissioning
procedure once again under operating conditions because part of the
machine data depends on the operating temperature.
When the unit is in "as-delivered" condition, the guided commis-
sioning procedure is started automatically. After successful commis-
sioning, the guided commissioning can be carried out again later via
the sub-menu CTRL.
• Use the ENT key to switch to the CTRL sub-menu.
• In the CTRL sub-menu, select the menu item "SEtUP" and con-
firm by pressing the ENT key.
• Use the ENT key to select parameter Configuration 30.
The available configurations are displayed automatically depending
on the selected
Control level 28.
• Use the arrow keys to enter the number of the required con-
figuration. (for a description of the configurations, refer to the
following chapter)
If the setup was changed, the hardware and software functionality
will be configured. The message "SEtUP" is displayed again.
Confirm this message by pressing the ENT key in order to continue
the commissioning procedure.
ENT
ENT
• Switch to the next parameter.
• After initialization, confirm the selected configuration by pressing the ENT key.
• Continue the guided commissioning procedure according to the following chap-
ters.