Rack and pinion hoist
Assembly and Operating Instructions
36 / 100 BL108 GB Edition 03.2018 Rev. 02
Assembly in front of a scaffolding
Anchoring distance V = 4m
Load capacity = max. 200kg
Scaffold bay depth = 0.7 m
Anchoring forces with maximum track projection
The values in the table apply for each anchorage point
Scaffold bay depth = 1.0 m
Anchoring forces with maximum track projection
The values in the table apply for each anchorage point
Adhere to rail bracket vertical distances of max. 4.0 m
During operation, the mast must not be moved to more
than a max. of 3 m beyond the last rail bracket. The
interlock lever of the top section of the ladder must be
open.
and identification