Préparation du site
1. Power considerations are shown in the following table:
Option Description
AC power
Ensure a suitable circuit breaker is in-line between the device and the
power source.
The main power supply must be installed by a qualified electrician,
according to power authority regulations. Make sure all powering is wired
with an earth leakage, according to local regulations.
It is recommended to install the device within 1.5m (approximately 5feet)
from an easily accessible grounded AC outlet.
DC power
Ensure a suitable circuit breaker is in-line between the device and the
power source.
Connect DC-input power supplies only to a DC power source that
complies with the product's DC powering specifications.
Ensure that power is removed from the DC circuit before installing or
removing power supplies.
2. Handling fiber channel cables:
Always read and comply with the handling instructions on the shipping container.
Follow all ESD precautions and approved fiber cleaning procedures.
The fiber is made of a very pure, expensive glass and should be treated with great care. Handle
fibers only in areas that are very clean and do not contain sharp objects.
Wear finger cots or gloves as dirt and oils can damage the fiber and contaminate connectors.
Do not allow kinks or knots to develop in the fiber. If tangles occur, carefully work out the tangles
avoiding pulling or bending the fiber beyond its bend radius.
Always use the correct tools for stripping and cleaving the fiber. It will save time and reduce
breakage caused by scratches.
If you must secure a bundle of fiber cables together, avoid plastic and metal tie wraps; secure with
Velcro instead.
3. Disposing of the unit:
Dispose of the unit and its components (including batteries) as specified by all national laws and
regulations.
Préparation du site
Préparez le site réservé à l’équipement en vue de son installation et utilisation.
NOTE: REMARQUE : seul du personnel de maintenance formé et qualifié (tel que défini dans
les normes IEC 60950, IEC 62368 et AS/NZS 3260) doit être autorisé à réaliser l’installation, le
remplacement ou la maintenance de l’équipement. Si vous vous trouvez aux États-Unis, installez le
système conformément aux normes NEC (National Electrical Code).
IMPORTANT: REMARQUE : Préparez le site pour une installation en toute sécurité
conformément aux règles de sécurité locales, à l'environnement d'installation et aux
spécifications du produit.
115 Installation Guide
D R A F T

Table of Contents

Related product manuals