(2) While holding both side of the bezel (arrowed A), pull out the bezel
from the lever.
Installing the bezel:
(3) While holding both side of the bezel (arrowed A), install and fix the
bezel to lever.
3. Turn on LID LED for identifying the target blade.
See Identify LED (LID) on/off procedure on page 4-7 section.
4. The rebuilding will start within one minute after installing the spare disk
drive. Verify the following LED status in the spare drive that the rebuilding
started.
¢
Active LED: blink in green
¢
Fault LED: blink in amber
5. Confirm the rebuild status. See
Identifying rebuild status on page 6-2
section.
6. Wait for rebuilding, and after thirty minutes to two hours, it will be
completed.
Replacing parts