Figure 6-2 Main window of internal storage monitor
Figure 6-3 Fault LED
4. Click Maintenance in internal storage monitor window, and then
confirm the progress of the rebuilding in Progress column of the middle
Logical Drive (LD) pane and right most Physical Drive (PD) pane.
5. Wait until rebuild progress state becomes 100% or indicates a hyphen.
6.
Click Dashboard > LD#
*
] > Logical Drive Information.
Confirm whether the rebuilding finished normally.
(Note: * Select the LD number on which the rebuild is executed.)
Identifying RAID rebuild status