1. When the direction of the refrigerant pipe is changed, add a support at the
position that is 1000 mm away from the changing point.
2. When the refrigerant pipe is straight, add a support every 2500 mm.
Figure 4-24 Securing supports
NO TE
Onsite personnel are responsible for preparing the required materials and installing the
supports.
Step 4 Connect the threaded connector.
FusionModule500 Smart Mini Data Center
User Manual 4 Installation Guide