4 Power-On Commissioning
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
50
4 Power-On Commissioning
4.1 Commissioning Preparations
Keep clear the dust and dirt position of the cabinet before the device start running, any dirty
position and foreign body in the water pan may cause pump congestion and poor drainage will
seriously affect the operation of the equipment.
1. All power parameters are the same as those specified in the nameplates, and power
cables are correctly connected.
2. Ensure that the active and standby power cables are correctly and securely connected.
4.2 Setting Parameter
4.2.1 Powering On the NetCol5000-C
Before commissioning the NetCol5000-C, learn about the functions and positions of circuit
breakers. Figure 4-1 shows the positions of the circuit breakers.