Before powering on the UPS, measure the voltage and frequency of the upstream
power distribution switch of the UPS cabinet. Ensure that the phase voltage is
within the range of 80–280 V AC and the frequency is within the range of 40–70
Hz.
Procedure
Step 1 Switch on the input circuit breaker QF.
Step 2 Switch on the UPS input circuit breaker QF1.
The UPS is powered by the mains and initialization begins. The LCD displays an
initialization progress bar.
----End
5.2.2 Initial Startup
If the equipment is started for the rst time, obtain authorization for the
equipment and set related parameters on the Settings Wizard screen. If the
equipment is not started for the
rst time, skip this section.
Procedure
Step 1 Obtain the startup password through the app. After the application is approved,
enter the password on the service authorization screen of the device to complete
device authorization.
Technical support engineers can obtain the service authorization code through the
app. For details, see the
Data Center Facility Deployment Guide
.
Step 2 Set the language, time and date, network parameters, system parameters, and
battery parameters on the Settings Wizard screen.
UPS5000-E-(30 kVA–180 kVA)
User Manual (Integrated UPS) 5 Operations
Issue 02 (2022-12-30) Copyright © Huawei Digital Power Technologies Co., Ltd. 126