COMMISSIONING6 - 1
D-MAXE with OI-B/OI-N www.maxcessintl.comMI 2-296 1 D
6 COMMISSIONING
Before commissioning
The following assembly and electrical connection tasks must be
performed before commissioning:
– The modules of the D-MAXE system must be assembled
properly.
– The modules of the D-MAXE system must be properly
connected to the power supply and integrated into the
'EMERGENCY STOP' circuit of the customer's system.
– The sensors and actuators must be properly connected to the
D-MAXE system.
– It is also important to become familiar with the basic
operation of the user interface (see
User interface, page 4-2
).
Commissioning Once all assembly and connection tasks have been checked and
are in proper condition, the D-MAXE system can be placed in
operation.
Also make certain before commissioning that
– Commissioning of the D-MAXE system is performed while
the web is stopped.
– No one is in the danger zone of the drives.
Note:
The D-MAXE system has been preset to the customer
application and checked before it leaves the factory.
However, this does not apply to replacement part deliveries.