90
F
ITTING THE COMMUNICATION SERVER
CHAPTER 4 INSTALLATION
Equipment supplied
The equipment supplied with the communication server includes:
• Mitel SMBC communications server with fitted CPU module and mounted fan
• Set of screws for wall or desktop installation and earthing connection
• Snap-on tag
• Power supply
• Power cord
• Product information
Mounting options
Mitel SMBC includes all the materials required for wall or desktop installation. Additional rack installation
sets are required for a 19” rack installation.
For wall mounting all the connecting cables can be concealed behind a cable cover. This set can be
ordered as an option.
Cable cover set
Equipment supplied:
• Cable cover
• Left-hand bracket for cable cover
• Right-hand bracket for cable cover
• Screw set
Mitel SMBC rack-mounting set
Equipment supplied:
• 2 mounting plates for rack installation
• Screw set
Location requirements
The following location requirements must be observed when positioning the communication server.
WARNING: Failure to observe the location requirements can cause the communication server to overheat,
damaging electrical components and/or the surrounding area.
An event message is generated if the heat dissipation is insufficient. Appropriate measures must be taken
immediately to improve the heat dissipation, e.g. by providing the required clearances or lowering the
ambient temperature.
Table 4.1:Location requirements (Sheet 1 of 2)
Heat radiation • Do not position in direct sunlight, near radiators or
near other heating sources