22 Site planning
• High handset density area
• Multiple systems installation
Site planning example: Able-Studio
This section describes a site survey for Able-Studio, a fictitious company.
Follow this example to conduct the site survey.
The facts for Able-Studio
• The contact is Rolf Sundby at 555-0000. A guest lab coat is necessary
to be on the site. Get this lab coat from Rolf.
• The sales representative has recommended DECT.
•
The location of user offices with wired IP phones often changes within
the coverage area.
•
Not all users have offices and desk phones. Some users only have
handsets.
• The customer does not need coverage in the washrooms.
•
The telephone switch room is next to the washrooms.
•
The customer has no installation restrictions.
The site survey process for Able-Studio
The technician must gather the following information to conduct a site
survey.
•
“Gather survey items” (page 22)
•
“Identify site contacts” (page 23)
•
“Obtain site plans” (page 23)
•
“Gather building information” (page 24)
• “Identify existing cabling” (page 25)
• “Profile handset use” (page 26)
Gather survey items
Obtain the following items before beginning the site survey. The items are
not customer supplied.
• Pick up the DECT tool kit (consisting of tripod and deployment tool kit).
• Get the appropriate DECT provisioning record.
• Gather a pencil, an eraser, a ruler, and colored pencils.
Nortel Communication Server 1000
SIP DECT Fundamentals
NN43120-123 01.07
6 January 2009
Copyright © 2008-2009 Nortel Networks
.