1. Installation Method
1-9
8) Checking the Installation (Securing the Instrument)
1. Confirm that the location where the instrument will be installed is flat and sufficiently strong.
2. Move the instrument to the installation location and lower the stoppers of the front casters of the instrument to
secure the instrument.
If enough space is left for people to pass through at the rear of the instrument, the users may touch the power
cord or hook it with their foot and accidentally cut off the power; accordingly, select a location where no
unnecessary large space will be left at the back of the instrument.
9) Installation Check (Installing the Accessories)
[1] Installing the spill tray (for paraffin oven)
Put the spill tray in the space below the paraffin oven and push it all the way in, as shown in the figure below.
[2] Installing the spill tray (for Reagent bottle rack)
Put the spill tray in the space below the Reagent bottle and push it all the way in, as shown in the figure below.