Chapter 5
MSC800
8011540/14B8/2019-06-06 Operating instructions | SICK 43
Subject to change without notice
5 Electrical installation
5.1 Overview of the installation steps
Completed mounting of the MSC800 is required for electrical installation
(see chapter 4 Mounting on page 37).
The following list gives an overview of the typical installation steps:
• Connect ICR890 and/or CLV490 system to supply voltage OUT
• Connect ICR890 and/or CLV490 system to MSC800 via CAN bus
• Connect MLG light grid (RS-485) or VMS4xx/5xx (CAN bus)
• Connect read cycle sensor(s)
• Connecting the incremental encoder
• Optional: wire switching outputs for system status display
• Connect host computer (RS-232, RS-422/485, Ethernet, or PROFIBUS-DP)
• Temporarily connect PC/laptop for commissioning and configuration (RS-232,
Ethernet, or USB)
• Connect mains voltage IN.
The actual work to be carried out depends on the relevant configuration in which the
MSC800 is used (see chapter 5.2 Electrical installation of the MSC800 on page 44).
After completion of the electrical installation, commissioning and configuration of the
MSC800 is carried out (see chapter 6.1 Overview of the commissioning steps on
page 73).
Important