3KC ATC6300 transfer control device
Manual, 03/2018, L1V30535632002A-01
145
Commissioning
10
The following chapter contains information on commissioning the ATC6300.
WARNING
Hazardous voltage. Will cause death or serious injury.
Turn off and lock out all power supplying this equipment before working on the device.
Replace all covers before power supplying this device is turned on.
Note
This description provides basic information regarding commissioning of the ATC6300.
The planning and dimensioning relat
ing to electrical requirements / standards of the control
cabinet are not described below.
Procedure
Ensure there is no live voltage before connecting the ATC6300.
1. Install the ATC6300 as described in chapter Installation (Page 63).
2. Attach any expansion modules that have been purchased in addition (see chapter
Expandability by modules (Page 41)).
3. Connect the ATC6300 according to your application, as described in chapter Connection
(Page 65).
4. Check whether all requirements have been implemented in accordance with the technical
specifications (conductor cross-sections etc.).
5. Check whether all electrical requirements relating to fuse protection, planning and
installation of the control cabinet have been implemented.
6. Close the control cabinet.
7. Switch on the power supply.
8. All the LEDs on the ATC6300 flash during startup.
9. When the ATC6300 has started up, set the date and time.
10. Press the ▲ and ▼ keys simultaneously to access the main menu and select the password
entry window.