Parameterization
9.3 Parameters
3KC ATC6300 transfer control device
Manual, 03/2018, L1V30535632002A-01
125
Designation on ATC
display
P05.01 Application type Type of application
This parameter specifies the type of applica-
tion and facilitates the management of the cor-
responding input / output signals.
U-G = Utility (network) / Generator
U-U = Utility (network) / Utility (network)
G-G = Generator / Generator
U-G U-G
U-U
G-G
P05.02 Priority line Selecting the priority line
– Specifies the priority line. It defines the line
through which the loads are supplied, if both
- 1 - -1- Line 1
-2- Line 2
P05.03 Line 1 -> 2 interlock Line 1 → Line 2 interlock time
– Delay that elapses between the disconnection
of breaker Line 1 and the opening command for
breaker Line 2. For example, if the breaker Line
1 is opened, there is a wait time of 6 seconds in
accordance with default settings for an opening
command to be sent to the breaker Line 2.
s 6.0 0.1 ... 1800.0
P05.04 Line 1 -> 2 interlock Line 1 ← Line 2 interlock time
– Delay that elapses between the disconnection
of breaker Line 2 and the opening command for
s 6.0 0.1 ... 1800.0
P05.05 Changeover re-
sponse
Changeover response
– This parameter defines the general conditions
for a changeover.
A selection can be made between OBP (Open
before presence) and OAP (Open after pres-
OBP OBP
1)
OAP
2)
P05.06 Feedback delay Maximum time for switch control -
Alarm delay A03 – A04
– If a switching device is not in the correct posi-
tion within this time following an ON or OFF
command, alarm A03 or A04 is triggered.
For more detailed information on the alarms,
please refer to chapter Alarms (Page 46).
s 5 1 … 900