3.12 Putting the Example into Operation
Commissioning
1. Switch on the power supply of the ET 200iSP.
2. Observe the status LED at the S7-400 and at the ET 200iSP:
LEDs of the CPU:
RUN: on (means: LED lights up)
All other LEDs: o󹪜 (means: LED does not light up)
For PROFINET con󹪝guration - LEDs on the interface module IM 152-1PN of the ET 200iSP:
ER: O󹪜
MT: O󹪜
ACT: O󹪜
RN: on
PS1: On, PS2: O󹪜
LK1 and/or LK2: on (when a network connection is set up from one device to another;
otherwise o󹪜)
For PROFIBUS con󹪝guration - LEDs on the interface module IM 152-1DP of the ET 200iSP:
SF: O󹪜
BF: O󹪜
ACT: O󹪜
ON: on
PS1: On, PS2: O󹪜
3.13 Evaluating the diagnostics
Evaluating the diagnostics
If an error occurs, OB82 is started. Evaluate the startup information in OB82.
Tip: Call the SFC13 within the OB82 and evaluate the diagnostics frame from section
"Commissioning and Diagnostics (Page 155)".
Commissioning guideline
3.13 Evaluating the diagnostics
ET 200iSP
Operating Instructions, 11/2022, A5E00247483-AK 55

Table of Contents

Other manuals for Siemens SIMATIC ET 200iSP

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens SIMATIC ET 200iSP and is the answer not in the manual?

Siemens SIMATIC ET 200iSP Specifications

General IconGeneral
BrandSiemens
ModelSIMATIC ET 200iSP
CategoryI/O Systems
LanguageEnglish

Related product manuals