Instruction Manual for AS380 Series Elevator Integrated Drive Controller
Chapter 8 Elevator Elevator Commissioning Guide
195
Chapter 8 Elevator Elevator Commissioning Guide
This chapter provides the guide for operation of elevator. Following the operation procedures
described in this chapter to complete the design, installation, wiring, parameter setting and
commissioning of elevator quickly.
Important
Any users of our products are required to carefully read and understand this manual and the
related equipment manuals of the system prior to starting system commissioning or putting it into
operation in order to avoid accidentals losses.
Be sure to read and understand the instructions for System Parameter Setting in this manual
prior to starting system commissioning or putting it into operation in order to avoid accident
losses.
Site commissioning can not be started until all mechanical equipment, especially shaft
equipments and devices are installed reliably (The equipment required in the machine room
depends on the preparation of machine room).
Any equipment and devices required to be installed and commissioned before system
commissioning shall be surely completed in a reliable manner.
Before commissioners starting its works, all the works must be confirmed by the related
installation persons and commissioning director of mechanical system and other system or by the
other persons designated to taking the related responsibilities.
Prior to system commissioning, the commissioner shall carefully check all the equipment and
other devices related to the commissioning of electric system are all completely installed and
commissioned appropriately.
Prior to system commissioning, the commissioner must carefully check there is not any
existences of unsafe factors to human body and property (including potential and possible unsafe
factors).
The commissioner must be of trained and qualified to execute commissioning of elevator
control system.
In case that this manual can not satisfy your requirements, please contact us timely to get
supporting in time.
Commissioner shall, before starting its work, check all the site conditions are ready to carry
out system commissioning.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the STEP AS380 Series and is the answer not in the manual?

STEP AS380 Series Specifications

General IconGeneral
BrandSTEP
ModelAS380 Series
CategoryController
LanguageEnglish

Related product manuals