MAINTENANCE SCHEDULE & PROCEDURES Model 400E Ozone Analyzer
Instruction Manual
210 P/N 04316 Rev: B
9.3.3. Replacing the IZS Zero Air Scrubber
Procedure:
1. Turn off the analyzer.
2. Remove the cover from the analyzer.
3. Disconnect the white nylon ¼”-1/8” fitting from the Zero Air Scrubber (See
Figure 9-2).
4. Remove the old scrubber by disconnecting the 9/16” fitting at the top of the O
3
generator tower, then removing the scrubber.
5. Install the new scrubber by reversing these instructions.
IZS Zero Air Scrubber
Figure 9-2: Replacing the IZS Zero Air Scrubber