Natrix IOM
• The Installation Supervisor must be experienced with
conveyor and qualified in the mechanics of the
equipment and enforce safe working procedures for the
protection of the crew, customer, and customer’s
Receiving & Site Preparation
General
TGW Systems Natrix Shoe Sorter are shipped in subassemblies. These subassemblies are
packaged to guard against damage in shipment, when handled properly.
Examination immediately following unloading will show if any damage was caused during
shipment. If damage is evident, claims for recovery of expenses to repair damage or replace
components must be made against the carrier immediately. While unloading, a check must be
made against the Bill of Lading, or other packing lists provided, to confirm full receipt of listed
items.
• TAKE CARE DURING THE REMOVAL OF EQUIPMENT FROM THE
CARRIER. Remove small items and boxes first. Pull and lift only on the
skid, not on the frame, cross member or any part of the equipment.
See examples below of packing units or structures.
Preparation of Site
After the conveyor is received, move it to the installation site or designated dry storage area as
soon as possible. Clean up all packing material immediately before parts get lost in it. Loose
parts should remain in the shipping boxes until needed.
Prior to starting assembly of the conveyor, carefully check the installation path to be sure there
are no obstructions that will cause interference. Check for access along the path needed to
bring in bed sections and components closest to the point where they are needed. It is often
necessary to give the area along the system path a general cleanup to improve installation
efficiency, access and accuracy.