Natrix IOM
Installation
Preparation
Define the start point.
Mark the center reference line on the floor.
Determine the top rail height.
Measure from the lowest point with in reference line of equipment installation and level
accordingly.
Installation of Infeed/Discharge belt conveyor supports
Install the supports according to the support layout.
Positioning of Infeed/Discharge Belt conveyor
Position the modules and align them to the correct top conveyor level.
(Do not anchor yet) Align frames for a smooth seamless transition.
Revision Date: 12/10/2014 Page 33 of 111