This chapter explains how to verify correct oscilloscope
operation and perform tests to ensure that the oscilloscope
meets the performance specifications.
Let the Equipment Warm Up Before Testing
For accurate test results, let the test equipment and the
oscilloscope warm up 30 minutes before testing.
Verifying Test Results
During the tests, record the readings in the Performance Test
Record on page 48. To verify whether a test passes, verify that
the reading is within the limits in the Performance Test Record.
If a performance test fails
If a performance test fails, first perform the User Cal procedure