Manual
 
 
KVCG202/EN M/H
 
 
9.9.1  Preliminary checks 
Loosen the four cover screws and remove the cover, the relay can now be withdrawn 
from its case. Carefully examine the module and case to see that no damage has 
occurred since installation and visually check the current transformer shorting switches in 
the case are wired into the correct circuit and are closed when the module is withdrawn. 
Check that the serial number on the module, case and front plate are identical and that 
the model number and rating information are correct. 
Check that the external wiring is correct to the relevant relay diagram or scheme diagram. 
The relay diagram number appears inside the case on a label at the left hand side. The 
serial number of the relay also appears on this label, and on the front plate of the relay 
module. The serial numbers marked on these three items should match; the only time 
that they may not match is when a failed relay module has been replaced for continuity of 
protection.  
With the relay removed from its case, ensure that the shorting switches between 
terminals listed below are closed by checking with a continuity tester. 
Terminals:   21 and 22; 23 and 24; 25 and 26; 27 and 28. 
9.9.1.1  Earthing 
Ensure that the case earthing connection, above the rear terminal block, is used to 
connect the relay to a local earth bar and where there is more than one relay the copper 
earth bar is in place connecting the earth terminals of each case in the same tier 
together. 
9.9.1.2  Main current transformers 
DO NOT OPEN CIRCUIT THE SECONDARY CIRCUIT OF A LIVE CT SINCE THE HIGH 
VOLTAGE PRODUCED MAY BE LETHAL TO PERSONNEL AND COULD DAMAGE 
INSULATION. 
9.9.2  Remote testing 
The relay can be communicated with from a remote point, via its serial port, then some 
testing can be carried out without actually visiting the site.  
9.9.2.1  Alarms 
The alarm status led should first be checked to identify if any alarm conditions exist. The 
alarm records can then be read to identify the nature of any alarm that may exist.  
9.9.2.2  Measurement accuracy 
The values measured by the relay can be compared with known system values to check 
that they are in the approximate range that is expected. If they are, then the 
analogue/digital conversion and calculations are being performed correctly.  
9.9.3  Local testing 
When testing locally, similar tests may be carried out to check for correct functioning of 
the relay. 
9.9.3.1  Alarms 
The alarm status led should first be checked to identify if any alarm conditions exist. The 
alarm records can then be read to identify the nature of any alarm that may exist. 
9.9.3.2  Measurement accuracy 
The values measured by the relay can be checked against known values injected into the 
relay via the test block, if fitted, or injected directly into the relay terminals. Suitable test 
methods will be found in Section 8.1 of this manual which deals with commissioning. 
These tests will prove the calibration accuracy is being maintained. 
9.9.3.3  Additional tests 
Additional tests can be selected only from the features that are to be used in the 
application these features are listed in the Commissioning test instructions as required.