Step 4 Install oating nuts for the end cabinet.
● The oating nuts are packed in the IT cabinet.
● Install oating nuts for other aisle side sealing plates in the same way.
Figure 4-26 Installing
oating nuts
Step 5 Install aisle side sealing plates on the end cabinet side facing the aisle exterior
using the screws removed in Step 1.
Figure 4-27 Installing aisle side sealing plates for an end cabinet
Step 6 Install aisle side sealing plates on the aisle exterior side of the other end cabinet in
the same way.
----End
FusionModule800 Smart Small Data Center
User Manual 4 Installation Guide
Issue 01 (2021-02-05) Copyright © Huawei Technologies Co., Ltd. 113