When you backfill on a slope, pile the material on the high side of the trench when possible.
Move the dozer blade level to the ground. Work at right angles to the trench, fill a dozer blades width at a time.
Leave any spillage until the trench is filled.
Use the spillage to finish the job by driving the length of the trench with the dozer blade low to the ground.