Preparing for use
22
Commissioning
The machine should be commissioned by a Miele service tech-
nician or an authorized Miele Service dealer only.
Open the supply valves for water and steam, depending on heating
type.
Switch the machine on at the on-site power switch.
Switch the machine on with the I Power On button.
PROFESSIONAL
PW 8xx
M
Welcome
The welcome screen will appear in the display.
1 Cottons Hygiene 194
2 Cottons Universal 140
3 Cottons Intensive 140
°F
°F
°F
Depending on the program selected, the following will appear in the
display:
Then the program list appears.
The last started program is highlighted.
Tip: Turn the multifunction selector to select a program and press the
"START" button to start it immediately.