Commissioning Manual
228 01/2017
You can check the commissioning status via the status symbols from the main screens of the commissioning wizards.
Completed task
Current task
Partially completed task group
Uncompleted task
The diagram below shows the general commissioning procedure for the NC.
Commissioning the prototype machine
Note
The control system constantly creates restoring points during op
eration. In case of data loss due to power failure or other
problems, the control system automatically restores the last autosaved system data upon startup with an alarm appearing on
the screen.
Note
Before starting the machine commissioning with the co
mmissioning wizard, make sure MD20050, MD20070, and MD35000