General Information on the SINUMERIK 840Di sl
1.3 Notes on startup
Manual
Commissioning Manual, 05/2008, 6FC5397–4CP10–4BA0
35
Additional hardware
The following hardware components are required for commissioning:
● Via the Ethernet interface, e.g. PG740:
– Creation of the SIMATIC S7 project for commissioning of the PLC, as well as the
PROFIBUS communication
– Installation of additional software on the PCU
For installing the software on the PCU see Section
"License management" (Page 146).
● Communications link: PG/PC with NC, PLC and drives
– Ethernet cable
Note
No programming device is required in the following cases:
• SIMATIC Manager STEP7 is installed on the SINUMERIK 840Di sl PCU
• A PG/PC is needed for installing additional software
For installing the software on the PCU see Section
"License
management" (Page
146).
Documentation
The following documentation is required for commissioning:
● /BH/ Operator Components Manual
– Operator panel fronts
– PCU 50.3
– Machine control panels
– Operator panel, handheld terminal HT8
Depending on the NC and PLC functions used, the corresponding function manuals are
needed:
● /FB/ Function Manual - Basic Functions
● /FB/ Function Manual - Extended Functions
● /FB/ Function Manual - Special Functions
● /LIS/ Lists
– Overview of functions
– Machine, Setting Data and Variables
– Interface Signals and PLC Blocks.
● /DA/ Diagnostics Manual:
– Interrupts