DRIVE TRAIN 4-13
• After reassembling the universal joint, check the joint move-
ment smoothly. If a large resistance is felt to movement, tap
the bearing with a plastic mallet lightly.
• Before installing the universal joint yoke assembly, place the
snap ring between the shifting sleeve and splines of universal
joint.
• Install the universal joint yoke assembly by tapping with a
plastic mallet.
• Fix the universal joint yoke with the snap ring.
2WD/4WD SHIFTING
• Install the 2WD/4WD shifting fork, springs and shifting rack as
shown.
• Apply sealant to the shifting fork shaft plug
1 and tighten it to
the specified torque.
& 99104-31140: SUZUKI BOND “1207B” (USA)
' 99000-31110: SUZUKI BOND “1215” (Others)
( Shifting fork shaft plug: 15 N·m (1.5 kgf-m, 11.0 lb-ft)