Emptying The pump station is used for emptying a container.
The diagram below shows the start, stop and supervision
levels for emptying. For simplicity, only three pumps are
shown. Parameter 79.02 Stopping mode is assumed to be
set to Common stop; 79.16 Start stop delay is assumed to be
set to 0.00 seconds.
1
No. Name/Value Description FbEq
Time
79.05 Stop level
79.06 Start 1 level
79.07 Start 2 level
79.03 Low level
79.08 Start 3 level
79.14 High level
Time
79.18 Normal speed
79.19 High speed
Frequency
Pump 3
Time
Frequency
Pump 1
Time
Frequency
Pump 2
79.18 Normal speed
79.19 High speed
79.18 Normal speed
79.19 High speed
Level (process actual value)