6.2.10 Controller is overheated
Required test equipment
Equipment needed for troubleshooting:
NoteEquipment
Multimeter
Insulating gloves
3HAC059896-009, 3HAC063898-009,
3HAC072448-009
Circuit diagram - OmniCore C30, Circuit dia-
gram - OmniCore C30 for IRB 14050, Circuit
diagram - OmniCore C30 for CRB 15000
Preparations
Action
Make sure that the controller is switched on.1
Wait 30 s - 1 min to enable start-up sequence.
Check the FlexPendant for errors and warnings.2
DANGER
Troubleshooting on the controller while powered on must be performed by personnel
trained by ABB or by ABB field engineers.
Recommended working procedure
If the controller seems to be overheated, use this procedure to troubleshoot what
might cause the problem.
Detailed working procedure
NoteAction
Replace malfunctioning fans, see
Replacing the standard fan on
page 239
Check that the standard fans are working.1
See Troubleshooting the power
unit on page 532 and Troubleshoot-
ing the drive unit on page 530.
If the problem remains, troubleshoot the power
unit and/or the drive unit.
2
Product manual - OmniCore C30 527
3HAC060860-001 Revision: P
© Copyright 2019-2022 ABB. All rights reserved.
6 Troubleshooting
6.2.10 Controller is overheated