COMMS TESTING
Comms > Comms Test >
Send Test Report
-
-
MENU 5-9-0
This menu allows you to test the reporting functions of
the control panel by manually sending a Test report to the
receiving party (i.e. security company monitoring station
).
1) Enter [MENU] + [5] + [9] + [0]. The keypad will
prompt that it is in the process of sending a test
report.
Comms Testing In
Progress ..Please Wait..
Press OK or MENU
2) If the test is successful, the keypad will prompt:
Comms Test Successful
Press OK or MENU
3) If the test fails, the keypad will prompt:
Test Report Failed..
Please Call For Service
Press OK or MENU
4) Press [OK] or [MENU] to exit.
Comms > Comms Test >
Test Report Time
MENU 5-9-1
Test Time
0 2 : 0 0
H H : M M
This menu programs the time of the day that the panel
will send the automatic Test Report to the base station
receiver. Automatic test reports are used to verify the
panels ability to report events via the telephone line on
an ongoing basis.
1) Press [MENU] + [5] + [9] + [1]. The keypad will
display the current Test Report Time.
Test Report Time
02:00am
Press OK to SAVE
2) Use the left, right, up and down arrow keys to
select the Test Report time required then press [OK]
to save and exit or press [MENU] to exit without
saving.
Scroll through the hours using the up and down
arrow keys to change the time from am to pm.