Consider the following key points when installing V2000:
1. Use the recommended grounding and LPU connections.
2. Use the recommended cables for interfacing ODU (refer to the supported power supply and cable
length details in the Power supply units (PSU) section).
3. Always install the ODU 0.5 meters below the tip of the pole.
Figure 68 shows a typical installation of V2000 CN on a mast and powered through outdoor AC/DC PSU.
Figure 68:
Typical installation - V2000 CN