8545-M838-O1 Rev D 825 Installation & Technical
INSTALLATION, CONT.
14. The shield wire is secured when tightening the gland connector nut. See Figure No. 9.
15. Do not over-tighten the connector but make certain it is snug.
Load Cell Cable Connection without RFI Suppression
The following instructions describe the load cell connection without RFI Suppression should it
not be required.
1. Remove the 14 acorn nuts securing the rear panel to the main housing.
2. Referring to Figure No. 2, choose a gland connector for the load cell cable and loosen it.
3. Slip the single cable from the load cell or load cell junction box through the gland connector
and into the enclosure.
4. Referring to Figure No. 4, remove 3 inches (not 6 inches) of the outer insulation jacket
5. Next, remove 1/4 inch of insulation from each of the six wires and shield (with sense leads)
or four wires and shield (with sense leads).
6. Referring to the table below and the labels on the circuit board for terminal connections,
connect each wire to the terminal block.
SHIELD (Connect the load cell cable shield wire here).
7. To terminate a wire, loosen the screws in the terminal block and then insert the wire into
the terminal opening. Tighten the screw to secure the wire in place. See Figure No. 7.
8. Repeat the procedure until all wires are in place.