128 WT.050.570.000.DE.IM.0714
Installation / Commissioning DEPOLOX
®
Pool
2.7
Commissioning proce-
dure
When the device has been mounted and the application selected, it can
be taken into operation.
The following table contains the individual commissioning steps in their
correct sequence.
More detailed information is contained in the sections listed in the "Re-
ference" column.
Completion of each step can be confirmed in the "Compl." column.
NOTE
If this installation sequence cannot be complied with, please contact
your contractual partner.
No. Step Reference Compl.
1 Fill the cell sand 2.7.1
2 Insert the sensors and connect 2.7.2
3 Connect the sample water 2.7.3
4 If membrane sensors are used, fit
the fine filter
2.7.4
5 Check the set mains voltage
adjust if necessary
2.7.5
6 Wire the device in accordance
with the selected application
2.12 and 2.7.5
7 Mount the labelling field in the
housing cover
2.7.6
8 Close the housing cover 2.7.7
9 Switch the device on 2.7.8
10 Set the application 2.7.8
11 If another operating mode is acti-
vated, switch to "MANUAL"
1.3.3
(Menu 3)
12 Select the language 1.3.3
(Display 1.6.1)
13 Set the date and time 1.3.3
(Display 1.6.1)
14 Enter the system name
(e.g. pool 1)
1.3.3
(Display 1.6.1)
15 Set the line diagram assignment 1.3.3
(Display 1.6.3)