Chapter A8: Quality Assurance Process and Maintenance
Definium AMX 700 X-Ray System 5161515-1EN Rev. 6 (10 February 2008) A8-10
Operator Manual © 2008 General Electric Company. All rights reserved.
13. Review the Status (far right column) of each test.
If all tests PASS: QAP is complete. Click [EXIT] to return to the Worklist screen and continue work.
If some tests FAIL: Refer to Failed QAP
(p. A8-10) for more information.
Figure A8-15 QAP Results screen
Failed QAP
In the event of failed QAP tests, wait 10 minutes and repeat the QAP procedure to confirm the failure.
Check the items listed below when repeating the tests:
• Check collimator blades. Make sure that they are fully open and not in the field of view.
• Check that the phantom is correctly positioned.
• Check that no other objects are in the field of view.
If a single failure is confirmed, call to schedule service. The system is operational, although inspection
and potential calibration are needed.
If multiple failures are confirmed, image quality may be affected; cease use of the unit and call for
immediate service.
FOR TRAINING PURPOSES ONLY!
NOTE: Once downloaded, this document is UNCONTROLLED, and therefore may not be the latest revision. Always confirm revision status against a validated source (ie CDL).