5.10.3 Temperature check 8.3
Note: High-performance equipment is essential for reliable
measuring results, because of the relatively rapid
temperature changes.
Temperature check:
Check the temperature during the disinfection phase and the
length of the phase when the disinfection temperature has
been reached, against the temperature curve on the Program
sheet supplied.
The measuring equipment must be capable of continuously
recording temperature and time.
When carrying out temperature checks, a measuring point
close to the machine's temperature sensor is recommended.
Attach two external temperature sensors to the controlling
sensor during process runs.
The temperature on the external temperature sensor must be
above 90°C for 1 min and complies with the machine's graph.
The temperature curve must be attached together with this
checklist and be mailed to a pre-defined Getinge Disinfection
AB database, but not be sent as an attachment to the
customer. Compare time and temperature with the machine's
graph.
5 PREVENTIVE MAINTENANCE
74 (128) TECHNICAL MANUAL GETINGE WD15 CLARO
<Doc_TEC><Doc_6001396902><Rev.I><Lang_en>

Table of Contents

Other manuals for Getinge GE15

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Getinge GE15 and is the answer not in the manual?

Getinge GE15 Specifications

General IconGeneral
BrandGetinge
ModelGE15
CategoryLaboratory Equipment
LanguageEnglish

Related product manuals