Cabinet Installation Check
Table 4-18 Cabinet installation check items
No. Check That Check Result
1 The cabinet layout position is consistent with the
equipment room layout diagram.
â–¡ Passed â–¡ Failed
2 All bolts are tightened, especially the bolts used
for electric connection. Flat washers and spring
washers are installed properly.
â–¡ Passed â–¡ Failed
3 The cabinet is clean and free of dust and other
materials.
â–¡ Passed â–¡ Failed
4 The cabinet is clear and complies with dustproof
requirements.
â–¡ Passed â–¡ Failed
5 The paint on the cabinet exterior is intact.
Promptly repaint the cabinet exterior if necessary
to prevent corrosion.
â–¡ Passed â–¡ Failed
6 The cabinet door and lock work properly. â–¡ Passed â–¡ Failed
7 All labels are correct, clear, and complete. â–¡ Passed â–¡ Failed
8 The cabinet has no waste tape, cable ties, paper,
or packing materials around it.
â–¡ Passed â–¡ Failed
9 All components are properly installed and no
component is left onsite.
â–¡ Passed â–¡ Failed
10 Block empty cable holes using plugs or lids. â–¡ Passed â–¡ Failed
Cable Installation Check
Table 4-19 Cable installation check items
No.
Check That Check Result
1 All cable joints are secured properly, especially the
cable joints between network cables.
â–¡ Passed â–¡ Failed
2 Exposed parts near the wiring terminals and lugs
are wrapped in PVC insulation tape or heat
shrinking tubing.
â–¡ Passed â–¡ Failed
3 The at washers and spring washers of all wiring
terminals are securely installed.
â–¡ Passed â–¡ Failed
4 Cables are bound neatly and cable ties are
secured evenly and properly.
â–¡ Passed â–¡ Failed
FusionModule800 Smart Small Data Center
User Manual 4 Installation Guide
Issue 01 (2021-02-05) Copyright © Huawei Technologies Co., Ltd. 247