Operation
Transporting the Machine
Figure 64. Method 3
E
E
K
B
B
B
B
A
A
G
F
C
D
H
J
A Front slew spine tie-down points B Rear undercarriage turret tie-down points
C Angle = 35° to 46° D Angle = 35° to 45°
E Angle = 9° to 15° F Length = 2,499mm to 1,846mm
G Length = 2,282mm to 1,670mm H Length = 2,500mm
J Slew ring centre line K Tie down decal
14.1. Make sure the straps are arranged at the correct angles and lengths.
14.2. Apply the correct lashing forces. Refer to Table 7.
15. Close the doors, windows, and covers on the machine and lock where possible to prevent accidental
opening during transport.
16. Remove both ramps and attach them in their transport position.
17. Raise any jacks to their transport position.