Figure 119. Installing the cable guide to the chassis
After you finish
Note: Change and save the new configuration information by using the Setup utility. When you turn on the 
server, a message indicates that the memory configuration has changed. Start the Setup utility and select 
Save Settings to save changes. See the ThinkSystem SR670 V2 Setup Guide for more information.
•  Complete the parts replacement. See “Complete the parts replacement” on page 328.
Network adapter replacement
Follow instructions in this section to remove and install a network adapter from or to the front I/O expansion 
board or the front I/O expansion board module.
Remove a network adapter
Follow instructions in this section to remove a network adapter from the front I/O expansion board or the 
front I/O expansion board module.
About this task
Attention: 
•  Read “Installation Guidelines” on page 121 and “Safety inspection checklist” on page 122 to ensure that 
you work safely.
•  Power off the server and peripheral devices and disconnect the power cords and all external cables. See 
“Power off the server” on page 14.
•  If the server is installed in a rack, slide the server out on its rack slide rails to gain access to the top cover, 
or remove the server from the rack. See “Remove the server from rack” on page 124.
Watch the procedure. A video of the installation and removal process is available: 
•  YouTube: 
https://www.youtube.com/playlist?list=PLYV5R7hVcs-BXei6L6c05osQVLt4w5XYx
•  Youku: https://list.youku.com/albumlist/show/id_59636529
Procedure
Step 1.  Prepare your server. 
Chapter 4. Hardware replacement procedures 179